SCADA control room monitoring screens
Work procedure

33 KV project with MPLS structure

RTU panel in the plant control room, IEC-104 over a BSNL or Airtel MPLS VPN to the SLDC.

Scope

What this project involves

A solar or wind plant evacuating power at 33 KV must report real-time generation data to the State Load Despatch Centre. In the MPLS structure, an RTU panel in the plant control room acquires the data and delivers it in IEC 60870-5-104 protocol over a BSNL or Airtel MPLS VPN circuit to the SLDC SCADA.

Typical application
  • Solar and wind plants connected to the grid at 33 KV
  • No utility PLCC or fibre path available from the plant
  • An ISP can deliver an MPLS circuit to site — wired or RF last mile

System architecture

PLANT CONTROL ROOM — 33 KV EVACUATIONModbusDIIEC-104Energy metersMFMs · Modbus RS485Breaker & isolatorStatus inputs (DI)RTU panelIEC-104 slaveGPS clockTime syncMPLS routerCPEMPLS VPNBSNL / AirtelSLDC SCADAIEC-104 master
Serial / hard-wired (RS485, RS232, I/O)Ethernet / LANMPLS VPN / leased circuitSwipe to see full diagram →
Procedure

8 stages, survey to handover

  1. 01

    Site survey & data collection

    STEL
    • Study the plant single line diagram, the 33 KV evacuation feeder and the connecting substation.
    • Confirm control-room space, DC supply (station battery / UPS) and earthing for the RTU panel.
    • List meters and transducers with CT / PT ratios; confirm Modbus availability on the MFMs.
    • Check MPLS feasibility at site with BSNL / Airtel — wired or RF last mile.
    Survey report Preliminary BOQ
  2. 02

    Point list & scheme approval

    STEL + SLDC
    • Prepare the signal list in the SLDC format — MW, MVAR, kV, Hz, feeder currents, breaker and isolator status, energy.
    • Prepare the RTU scheme and communication drawing.
    • Submit to SLDC / TRANSCO and obtain approval.
    • Obtain IP addressing and IEC-104 parameters (common address, IOA map) from the SLDC.
    Approved point list Scheme drawing IP plan
  3. 03

    MPLS VPN circuit provisioning

    STEL + ISP
    • Apply for the MPLS VPN circuit between plant and SLDC — as empanelled BSNL system integrator for AP & TS circles.
    • Arrange the last mile to the plant — copper, fibre or RF link.
    • Install the router / CPE and complete the circuit acceptance test.
    • Verify VPN reachability to the SLDC front-end.
    Circuit ID Acceptance test report
  4. 04

    RTU panel engineering & FAT

    STEL
    • Panel GA and wiring drawings; RTU (Schneider MiCOM C264C / Siemens / Synergy) with DI / DO cards.
    • Modbus interface to the MFMs, GPS time synchronisation, SMPS / DC-DC supply and MCBs.
    • Panel assembly and factory acceptance test (FAT) before dispatch.
    FAT report Panel drawings
  5. 05

    Installation at site

    STEL
    • Erect and earth the RTU panel in the control room.
    • Lay and terminate control cables (status / commands), CT / PT to meters and transducers, and the RS485 bus — ferruled and dressed.
    • Connect the DC supply; place and patch the router.
    Installation checklist Cable schedule
  6. 06

    RTU configuration

    STEL
    • IEC 60870-5-104 slave configuration — IP address, TCP port 2404, common address and IOA map as per the approved point list.
    • Modbus master polling of the MFMs; scaling and deadbands.
    • Time synchronisation (GPS / SNTP) and event logging.
    RTU configuration backup
  7. 07

    Point-to-point & end-to-end testing

    STEL + SLDC
    • Point-to-point test of every signal, from field device to RTU.
    • End-to-end test with the SLDC over MPLS — every IOA checked on the SLDC SCADA display.
    • Compare MW / MVAR on the meter and at the SLDC; verify scaling.
    • Link failure and reconnection test.
    Point-to-point test report End-to-end test report
  8. 08

    Commissioning & handover

    STEL + SLDC + Client
    • Joint commissioning with SLDC engineers and SLDC confirmation of data availability.
    • As-built drawings, final point list, O&M manual and operator training.
    • Annual Maintenance Contract.
    Commissioning report Handover dossier

Testing & commissioning checklist

  • Insulation resistance of control cables before energising
  • Panel earthing continuity
  • DC supply polarity and voltage at the RTU
  • Every digital input operated from the field and seen at the RTU and at the SLDC
  • Analog values compared with the meter display at different load levels
  • Time-stamp accuracy against GPS
  • IEC-104 connection re-established after a link or power interruption

Documents handed over

  • Approved point list and IOA map
  • RTU scheme and communication drawings
  • Panel GA and wiring drawings (as built)
  • FAT, point-to-point and end-to-end test reports
  • RTU configuration backup
  • MPLS circuit details and ISP escalation contacts
  • O&M manual and training record
Reference projects

Delivered by STEL

17 plants integrated to the SLDC over MPLS VPN circuits:

  • Bhagyanagar India Limited, Munipally
    5 MW SolarAirtel MPLS VPN TS SLDC
  • RMR Solar Energy Pvt. Ltd.
    1 MW SolarAirtel MPLS VPN TS SLDC
  • MLR Industries Private Limited
    2 MW SolarBSNL MPLS VPN TS SLDC
  • MSR Mega Bio Power Limited
    7.5 MW SolarBSNL MPLS VPN TS SLDC
  • Hyderabad Chemical Products Private Limited
    1.5 MW SolarBSNL MPLS VPN TS SLDC
  • Peritus Corporation Private Limited
    2 MW SolarBSNL MPLS VPN TS SLDC
  • Tropical Flavours Pvt. Ltd.
    1 MW SolarBSNL MPLS VPN TS SLDC
  • Valens Molecules Pvt. Ltd.
    1 MW SolarBSNL MPLS VPN TS SLDC
  • Heritage Foods Ltd.
    2.34 MW SolarBSNL MPLS VPN TS SLDC
  • Hetero Labs Pvt. Ltd.
    4 MW SolarBSNL MPLS VPN TS SLDC
  • Pragathi Group
    9 MW SolarBSNL MPLS VPN TS SLDC
  • Prashanth Narayan G (PNG Solar Power Plant, Sirgapoor)
    7 MW SolarBSNL MPLS VPN TS SLDC
  • M/s. Srinivasa Green Energies Private Limited
    2 MW SolarBSNL MPLS VPN TS SLDC
  • VCarve Renewable Energy Pvt. Ltd.
    3 MW SolarMPLS VPN TS SLDC
  • Hyderabad Institute of Oncology Pvt. Ltd., Khammam
    1 MW SolarBSNL MPLS VPN TS SLDC
  • Dartyens Power Pvt. Ltd.
    1 MW SolarAirtel MPLS VPN TS SLDC, Vidyutsoudha
  • Photon Energy
    5.5 MW SolarAirtel MPLS VPN TS SLDC, Vidyutsoudha

Next: 132 KV project with OPGW

Main & standby RTUs, PDH MUX and OPGW fibre on the 132 KV line — data, tele-protection and voice.